The Lagos State Government has reopened the Adetokunbo Ademola stretch of Ozumba Mbadiwe Road, connecting the 1004 area to Sir Samuel Manuwa Street on Victoria Island, following the completion of rehabilitation work.
The Senior Special Assistant to Governor Babajide Sanwo-Olu on New Media, Jubril Gawat, announced the reopening in a post on X on Saturday.
OZUMBA MBADIWE (ADETOKUNBO ADEMOLA BY 1004) NOW FULLY OPEN 🚧
Earlier today, the Lagos Office of Infrastructure and Lagos Ministry of Transportation led by the Special Adviser Infrastructure, Engr Olufemi Daramola have opened the Adetokunbo Ademola (1004) Section of the Ozumba Mbadiwe which was done all the way down to Sir Samuel Manuwa street, Victoria Island.
The Special Adviser, on behalf of Mr Governor thanked Lagosians for their patience all through this period, he says this critical section was scheduled to be done in 35 days and it was eventually done in 33 Days.
All further works on the Ozumba axis will be done after the festive season by next year.
#OzumbaRepairs
#LagosTraffic
#GreaterLagosRising@jidesanwoolu @followlastma
— Jubril A. Gawat (@Mr_JAGs) November 21, 2026
He said officials from the Lagos State Office of Infrastructure and the Ministry of Transportation, led by the Special Adviser to the Governor on Infrastructure, Olufemi Daramola, reopened the road earlier in the day.
According to Gawat, the rehabilitation was completed in 33 days, two days ahead of the 35-day schedule initially announced by the state government.

The project was part of efforts to improve road conditions and ease traffic movement along the busy Ozumba Mbadiwe corridor, which links Victoria Island with other parts of Lagos.
Before construction began, the government announced a 35-day traffic diversion to give contractors access to the affected stretch.Â
Motorists were advised to use alternative routes, while temporary changes were introduced around Adetokunbo Ademola Street, Civic Centre and Sir Samuel Manuwa Street.
Gawat said the Special Adviser, on behalf of the governor, appreciated residents for their patience and cooperation throughout the construction period.
He added that rehabilitation work on other sections of the Ozumba Mbadiwe corridor would continue after the 2027 festive season.